Direkt zum Hauptbereich

Measuring time efficiency in projects

We commonly rate a project’s success based on whether it is on time and in budget. But, as common as these KPIs are, they may not be good measures. As Jan Fischbach has shown, delays and budget overruns can look like project failure even though the benefits vastly exceed the costs and vastly outmatch the benefits of an on-time project./1/ Furthermore, a project can be on time, but lousy at using the available time efficiently. Isn’t something wrong when a project only requires small total effort, but takes months to finish?


Fortunately, there is a simple way to measure the time efficiency of projects. I’ll call this indicator “project duration efficiency” (PDE), which compares effort (hours or days worked) with duration (calendar time)./2/

In an ideal world, all effort would flow seamlessly from task to task, and in optimally matched, parallel streams. Thus, the project duration would be the sum of the effort of one stream: 20 days invested by 3 persons each of would result in a finished product in 20 days’ time (and a total effort of 60 person days). Put another way, every hour spent on the project contributed productively to the product’s creation. This utopia would look like this:


The PDE is a simple calculation:
PDE = normalized effort /  duration

To keep the results comparable, we normalize the effort by dividing the number of people involved by the total effort./3/ A project with 6 persons working a total of 120 person days would have a normalized effort of 20 days. If this project takes 8 weeks (40 workdays) in duration to complete, its PDE equals 20/40 or 0.5. It might look like this:

So, the final, full equation would be:
PDE = (total effort / number of people working on project) / duration

The best possible result is 1, although this value is rare.

Why is this KPI important? It shows us how efficiently we are using calendar time for delivering our results. It is based on the premise “fast delivery means early benefits”. PDE thus helps us see the cost of delay (CoD) in a project. CoD occurs when we deliver a project’s results later than they could have been delivered. It is equal to the benefits we forego by not having the product on the market. For example, a company is developing an innovative widget. If it forecasts selling €10,000 worth of new widgets each day, then each day that the project is late incurs a CoD of €10,000./4/

In the project example above, the “possible completion” date is the point at which we could have started reaping the benefits if the work had been organized to eliminate the gray days. I am aware that this ideal situation will appear impossible to many readers./5/ But, Scrum teams achieve massive productivity gains precisely through the compression of the gray boxes to near zero./6/

The measure does not distinguish between time lost due to poor scheduling, from project delays whatever their cause. From a CoD perspective, it doesn’t matter why we deliver late, our customers still can’t buy the widget. PDE is thus the starting point for the investigation. Of course, every project manager or team feels any delay with full force. We’re under pressure to deliver, and trivial delays like scheduling a workshop can drive us bats. We know it’s endangering the delivery date, and we know this long before the steering committee has asked about it. So why do we need to calculate the PDE?

PDE has many uses. With it, we can compare projects to each other objectively, since PDE is calculated from simple, observable facts. In a status report, it highlights schedule slippage to the steering committee, hopefully provoking a thoughtful discussion about priorities. And, in a large project, it might signal trouble ahead before it is too late. Across the whole company, the PDE can reveal that overall throughput is suffering. The cause is likely too much work in progress. Again, a review of priorities is in order.

PDE also helps in evaluating and adjusting estimates. Let’s assume, for example, that a company completed 25 projects last year. The average PDE value was 0.15, with most projects falling between 0.10 and 0.20. This company’s projects will thus have durations of 5 to 10 times their normalized efforts. If a director says, “we’ve budgeted 5 people for a total of 200 days, I expect this project to be finished in 2 months”, we can show that this is unrealistic.

This approach is similar to and compatible with velocity calculations in agile methods. Please note, PDE does not attempt to measure productivity in terms of completed items (say, story points). Rather, it’s focus is on time slippage only. Like velocity, however, it gives a transparent view of our schedule performance. That way, we know what we’re able to do under the current circumstances. Like any good KPI, it's just an honest measure. What we do with the result is up to us.

As always, feedback is welcome.  What is the PDE of the projects in your organization?

Part 2 of this series, you may find here: Measuring Project Duration Efficiency pt. 2 – a practical example


/1/ Jan Fischbach, Die zwei wichtigsten Regeln für IT-Projekte, Wie Sie mit zwei Regeln mehr Erfolg und weniger Stress haben, appearing in HR Performance, S. 60-63, Ausgabe 6/2014, which can be ordered at www.datakontext.com.

/2/ This metric is similar to value stream calculations in Lean approaches.

/3/ Who do we include? I recommend including everyone who is invoicing or actively recording her time for the project. The project manager should be included. The steering committee will usually be excluded. Most important for cross-project comparisons is a consistently applied definition.
We can find the data for PDE easily. Most companies a system for recording time, and the project manager is often responsible for controlling the time and/or preparing the data for invoicing. If no time recording is available, a simple tally sheet could be posted in the project office. To figure the duration take a look at a calendar: when was the kick-off and what’s the date today?

Note, we count the persons involved and not the number of planned FTEs. To understand why, let’s assume the example above is going exactly according to plan. Thus, each person is working a scheduled 50% for the project. With that we would tempted to divide the total effort by 3 FTEs instead of 6 persons.  The result would be 40 days of normalized effort, for a PDE of 1. With that, the index tells us nothing.

/4/ The best source on CoD is Donald G Reinertsen, The Principles of Product Development Flow: Second Generation Lean Product Development (Redondo Beach, Calif.: Celeritas, 2009).
Cost of delay is a vital measure for prioritizing products (or projects). The product with the highest cost of delay should be finished first, so that we can deliver it as early as possible.

/5/ Perhaps, you might argue, the team is working effectively on a second project during the gray days. Yes, of course, this seems efficient from a resource point of view. But, from a benefits or a cost-of-delay perspective it is not. We need to recognize that project 2 is also delayed, namely, during the colored days of project 1. So, why not dedicate the whole team first to project 1 and then to project 2? That way, we start to realize the benefits from project 1 after 20 workdays. The benefits from project 2 come after 40 workdays in either scenario.

/6/ The compression is possible for main two reasons: 1) the teams are dedicated to a product and are thus not distracted by multiple projects; 2) the teams are cross-functional, so that when one person gets delayed, others can step in and take on their tasks. See Jeff Sutherland, Scrum: The Art of Doing Twice the Work in Half the Time (New York: Crown Business, 2014).

Kommentare

Beliebte Posts aus diesem Blog

Wie lassen sich Ergebnisse definieren? - Drei Beispiele (WBS, CBP und BDN)

Ich habe schon darüber geschrieben, warum das Definieren von Ergebnissen so wichtig ist. Es lenkt die Aufmerksamkeit des Projektteams auf die eigentlichen Ziele. Aber was sind eigentlich Projektergebnisse? In diesem Beitrag stelle ich drei Methoden vor, um leichter an Ergebnisse zu kommen.

Microsoft Teams: Die neuen Besprechungsnotizen - Loop-Komponenten

  Haben Sie in letzter Zeit in einer Teams-Besprechung die Notizen geöffnet? Dort sind inzwischen die Loop-Komponenten hinterlegt. Die sind zwar etwas nützlicher als das, was zuvor zur Verfügung stand. Trotzdem ist noch Luft nach oben. Und es gibt sogar einige ernstzunehmende Stolperfallen. Hier ein erster, kritischer Blick auf das was Sie damit tun können. Und auch darauf, was Sie besser sein lassen.

Schätzungen sind schätzungsweise überschätzte Schätze

"Wer viel misst, misst viel Mist." Zumindest ist diese Gefahr gegeben. Entweder misst man z. B. Mist, weil man zu früh zu KPIs zur Messung von Ergebnissen greift, oder aber man greift zu den falschen KPIs, die gar nicht das messen, was man wissen möchte. Einst war agiles Arbeiten der alternative Ansatz, aber inzwischen gibt es auch für einige Details dessen, was in Konzernen als "agil" praktiziert wird, einleuchtende alternative Ideen, die bis heute noch nicht so richtig auf die große Bühne vorgedrungen zu sein scheinen. 

Microsoft Copilot - Notebook, Pages, Agents und mehr

Es tut sich sehr viel an der Copilot Front. Gefühlt entwickelt Microsoft mit aller Kraft die KI-Anwendung weiter. Mit dem letzten Update hat sich die Microsoft-Startseite stark verändert. Hier zeige ich, was sich hinter all den Begrifflichkeiten verbirgt und was davon alltagstauglich ist.

Wenn es mal gerade etwas schwierig bei Kund:innen wird… Zwei Fragen, die uns helfen, unsere Strategie mit unseren Kund:innen abzusprechen.

Seit 2024 organisieren Bob Galen und ich eine Masterclass für agile Coaches. Wir möchten die Ausbildung von agilen Coaches verbessern und ihnen Techniken mitgeben, mit denen sie bei ihren Kund:innen etwas einfacher haben. Bisher haben wir in vier Durchgängen mit jeweils 14 Modulen ungefähr 70 Extraordinarily Badass Agile Coaches ausgebildet (/1/). In diesem Blogpost möchte ich ein paar Erfahrungen und simple Techniken aus der Masterclass teilen, wie wir unsere Strategie besser abstimmen können. Sie beschränken sich nicht auf agiles Coaching – das ist nur das Setting.

Teamleitungen gesucht

Was macht Teams erfolgreich? Kann man das lernen? Ab Herbst starten unsere Kurse für aktuelle und künftige Teamleitungen. Jetzt gibt es die Gelegenheit, den Kurs zu testen.

Nachschau zum Lean Coffee-Spezial "Agil einfach machen" (Interaktive Buchvorstellung)

Bei unserem Lean Coffee-Spezial Ende Mai waren wir von Lean Coffee Karlsruhe/Frankfurt Zeugen einer Buchvorstellung, doch nicht nur das – natürlich gab es auch einen nicht unbeträchtlichen Anteil an eigener Aktion, denn bei unseren Spezialterminen ist traditionell „Teilgabe“ angesagt. Das Autorenduo Christian Baron und Janick Oswald zeigte uns, was es mit „Agil einfach machen“ auf sich hat.  

Wie überprüft man den aktuellen Stand einer neuen gemeinsamen Ablage?

Ihr habt in eurem Team die individuellen, unordentlichen Ablagen auf eine gemeinsame Ablage, die nach Vorgängen und Prozessen geordnet ist, umgestellt. Woher wisst ihr, ob das wirklich funktioniert? In diesem Beitrag gibt es 10 Auditfragen.

Intelligent filing

Most digital workplaces are disorganized. Important documents are scattered, there are too many emails in the inbox, and information is fragmented across different chats and boards. The consequence is that if you search for information, you have to visit all these different places. Still, you won't be sure you'll find it. Fortunately, there is a better way to structure your digital workplace. This method is more than 200 years old. It still works really well.